Substation Scout

Not reported

BPA queue ID G1013 Terminal status

Queue IDG1013
Project nameNot reported
Status (as published)WITHDRAWN
SubstationCombine Hills II tap to Walla Walla-Pendleton No 1 line
Point of interconnectionCombine Hills II tap to Walla Walla-Pendleton No 1 69 kV line
CountyUmatilla
StateOR
Voltage69 kV
Capacity250.1 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2030-12-31
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiCombine Hills II tap to Walla Walla-Pendleton No 1 69 kV line
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total250.1
Max Summer Mw250.1
Max Winter Mw250.1
ClusterTransition Cluster
Reason Not Completed.

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.