Substation Scout

Not reported

BPA queue ID G1005 Terminal status

Queue IDG1005
Project nameNot reported
Status (as published)WITHDRAWN
SubstationMcNary-John Day No 2 line
Point of interconnectionMcNary-John Day No 2 500kV line
CountyKlickitat
StateWA
Voltage500 kV
Capacity225 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2028-04-14
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiMcNary-John Day No 2 500kV line
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total380
Max Summer Mw225
Max Winter Mw225
ClusterTransition Cluster
Reason Not Completed.

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.