Substation Scout

Not reported

BPA queue ID G1000 Terminal status

Queue IDG1000
Project nameNot reported
Status (as published)WITHDRAWN
SubstationMcNary Substation, or Longhorn Substation
Point of interconnectionMcNary Substation, or Longhorn Substation
CountyMorrow
StateOR
VoltageNot reported
Capacity440 MW
Resource (as published)Solar/Photovoltaic
Resource categorySolar (normalised for filtering)
Target commercial operation2029-12-31
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiMcNary Substation, or Longhorn Substation
Generator TypePhotovoltaic
Fuel SourceSolar
Nameplate Mw Total660
Max Summer Mw440
Max Winter Mw440
ClusterTransition Cluster
Reason Not Completed.