1100MW Grizzly

BPA queue ID G10 Terminal status

Queue IDG10
Project name1100MW Grizzly
Status (as published)WITHDRAWN
SubstationGrizzly Substation
Point of interconnectionGrizzly 500 kV Substation
CountyJefferson
StateOR
Voltage500 kV
Capacity1,100 MW
Resource (as published)Natural Gas/Gas Turbine
Resource categoryGas (normalised for filtering)
Target commercial operation2004-07-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

RequestorCogentrix Energy, Inc.
Connection TypeGI
Interconnection TypeEnergy
PoiGrizzly 500 kV Substation
Generator TypeGas Turbine
Fuel SourceNatural Gas
Nameplate Mw Total1100
Max Summer Mw1100
Max Winter Mw1100
Reason Not Completed.