Not reported
BPA queue ID G0986 Terminal status
| Queue ID | G0986 |
|---|---|
| Project name | Not reported |
| Status (as published) | WITHDRAWN |
| Substation | Primary: Sedro-Woolley - Bellingham No 1 line; Secondary: Murray - Custer No 1 line. |
| Point of interconnection | Primary: Sedro-Woolley - Bellingham No 1 230kV line; Secondary: Murray - Custer No 1 230kV line. |
| County | Skagit |
| State | WA |
| Voltage | 230 kV |
| Capacity | 150 MW |
| Resource (as published) | Wind Turbine/Wind Turbine |
| Resource category | Wind (normalised for filtering) |
| Target commercial operation | 2029-12-30 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Connection Type | GI |
|---|---|
| Poi | Primary: Sedro-Woolley - Bellingham No 1 230kV line; Secondary: Murray - Custer No 1 230kV line. |
| Generator Type | Wind Turbine |
| Fuel Source | Wind Turbine |
| Nameplate Mw Total | 300 |
| Max Summer Mw | 150 |
| Max Winter Mw | 150 |
| Cluster | Transition Cluster |
| Reason Not Completed | . |