Not reported

BPA queue ID G0974

Queue IDG0974
Project nameNot reported
Status (as published)STUDY
SubstationParkdale Substation
Point of interconnectionParkdale Substation
CountyWasco
StateOR
VoltageNot reported
Capacity250 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2029-12-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeERIS
PoiParkdale Substation
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total255.2
Max Summer Mw250
Max Winter Mw250
ClusterTransition Cluster
Reason Not Completed.
CommentsLowerC1 Study Area