Not reported

BPA queue ID G0955

Queue IDG0955
Project nameNot reported
Status (as published)STUDY
SubstationTBD
Point of interconnectionTBD
CountyLincoln
StateWA
VoltageNot reported
Capacity350 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2026-09-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiTBD
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total357
Max Summer Mw350
Max Winter Mw350
ClusterTransition Cluster
Reason Not Completed.
CommentsNorth1 Study Area

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.