BPA queue ID G0935 Terminal status

Queue IDG0935
Project nameNot reported
Status (as published)WITHDRAWN
SubstationCentral Ferry-Lower Monumental No 1 Line
Point of interconnectionCentral Ferry-Lower Monumental No 1 500 kV Line
CountyWalla Walla
StateWA
Voltage500 kV
Capacity225 MW
Resource (as published)Solar/Photovoltaic
Resource categorySolar (normalised for filtering)
Target commercial operation2027-09-15
Source datasetbpa-generation

Tracked changes

1 change observed between weekly snapshots of the BPA queue since BPA tracking began on September 22, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-12 Terminal status 225 STUDY → WITHDRAWN

Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiCentral Ferry-Lower Monumental No 1 500 kV Line
Generator TypePhotovoltaic
Fuel SourceSolar
Nameplate Mw Total229
Max Summer Mw225
Max Winter Mw225
ClusterTransition Cluster
Reason Not Completed.
CommentsTricities/Umatilla1 Study Area