Substation Scout

Not reported

BPA queue ID G0923 Terminal status

Queue IDG0923
Project nameNot reported
Status (as published)WITHDRAWN
SubstationLower Monumental – Little Goose No 1 line. Alternates: Lower Monumental – Little Goose No 2 line; Little Goose – Central Ferry No 2 line
Point of interconnectionLower Monumental – Little Goose No 1 500 kV line. Alternates: Lower Monumental – Little Goose No 2 500 kV line; Little Goose – Central Ferry No 2 500 kV line
CountyWalla Walla
StateWA
Voltage500 kV
Capacity100 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2027-09-15
Source datasetbpa-generation

Tracked changes

1 change observed between weekly snapshots of the BPA queue since BPA tracking began on September 22, 2026. MW is nameplate as filed; for a capacity revision it is the change, not the new total.

DetectedChangeMWStatus was → now
2026-10-12 Terminal status 100 STUDY → WITHDRAWN

Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiLower Monumental – Little Goose No 1 500 kV line. Alternates: Lower Monumental – Little Goose No 2 500 kV line; Little Goose – Central Ferry No 2 500 kV line
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total307.4
Max Summer Mw100
Max Winter Mw100
ClusterTransition Cluster
Reason Not Completed.
CommentsTricities/Umatilla1 Study Area