BPA queue ID G0819 Terminal status

Queue IDG0819
Project nameNot reported
Status (as published)WITHDRAWN
SubstationColumbia-Grand Coulee No 1 line
Point of interconnectionColumbia-Grand Coulee No 1 230kV line
CountyDouglas
StateWA
Voltage230 kV
Capacity200 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2027-12-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiColumbia-Grand Coulee No 1 230kV line
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total200
Max Summer Mw200
Max Winter Mw200
ClusterTransition Cluster
Reason Not Completed.