Not reported
BPA queue ID G0804 Terminal status
| Queue ID | G0804 |
|---|---|
| Project name | Not reported |
| Status (as published) | WITHDRAWN |
| Substation | BPA's Gardiner Substation or Tahkenitch Substation. |
| Point of interconnection | BPA's Gardiner 115 kV Substation or Tahkenitch 115 kV Substation. |
| County | Douglas |
| State | OR |
| Voltage | 115 kV |
| Capacity | 200 MW |
| Resource (as published) | Biofuel/Reciprocating Engine |
| Resource category | Other (normalised for filtering) |
| Target commercial operation | 2028-12-08 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Connection Type | GI |
|---|---|
| Interconnection Type | NRIS & ERIS |
| Poi | BPA's Gardiner 115 kV Substation or Tahkenitch 115 kV Substation. |
| Generator Type | Reciprocating Engine |
| Fuel Source | Biofuel |
| Nameplate Mw Total | 200 |
| Max Summer Mw | 200 |
| Max Winter Mw | 200 |
| Cluster | Transition Cluster |
| Reason Not Completed | . |