Not reported

BPA queue ID G0749 Terminal status

Queue IDG0749
Project nameNot reported
Status (as published)WITHDRAWN
SubstationGarrison Substation
Point of interconnectionGarrison 230 kV Substation
CountyPowell
StateMT
Voltage230 kV
Capacity300 MW
Resource (as published)Solar/Photovoltaic
Resource categorySolar (normalised for filtering)
Target commercial operation2025-12-31
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeERIS
PoiGarrison 230 kV Substation
Generator TypePhotovoltaic
Fuel SourceSolar
Nameplate Mw Total600
Max Summer Mw300
Max Winter Mw300
Reason Not Completed.

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.