Not reported

BPA queue ID G0742 Terminal status

Queue IDG0742
Project nameNot reported
Status (as published)WITHDRAWN
SubstationVantage - Hanford No 1 line; Midway - Rocky Ford No 1 line; Midway - Potholes No 1 line.
Point of interconnectionVantage - Hanford No 1 500 kV line; Midway - Rocky Ford No 1 230 kV line; Midway - Potholes No 1 230 kV line.
CountyGrant
StateWA
Voltage500 kV
Capacity300 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2026-06-30
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiVantage - Hanford No 1 500 kV line; Midway - Rocky Ford No 1 230 kV line; Midway - Potholes No 1 230 kV line.
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total300
Max Summer Mw300
Max Winter Mw300
Reason Not Completed.