Substation Scout

Not reported

BPA queue ID G0735 Terminal status

Queue IDG0735
Project nameNot reported
Status (as published)WITHDRAWN
SubstationAberdeen Substation ; Alternatives: Satsop-Aberdeen No 2 line and Satsop-Aberdeen No 3 line
Point of interconnectionAberdeen Substation 230 kV; Alternatives: Satsop-Aberdeen No 2 230 kV line and Satsop-Aberdeen No 3 230 kV line
CountyGrays Harbor
StateWA
Voltage230 kV
Capacity500 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2030-05-30
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiAberdeen Substation 230 kV; Alternatives: Satsop-Aberdeen No 2 230 kV line and Satsop-Aberdeen No 3 230 kV line
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total1000
Max Summer Mw500
Max Winter Mw500
Reason Not Completed.

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.