Substation Scout

Not reported

BPA queue ID G0727 Terminal status

Queue IDG0727
Project nameNot reported
Status (as published)WITHDRAWN
SubstationCentral Ferry Substation Alternate POI: Tucannon River POI
Point of interconnectionCentral Ferry Substation 230 kV Alternate POI: Tucannon River POI 115 kV
CountyGarfield
StateWA
Voltage230 kV
Capacity0 MW (0 MW as filed — net change or energy-only)
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2026-12-31
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeERIS
PoiCentral Ferry Substation 230 kV Alternate POI: Tucannon River POI 115 kV
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total300
Max Summer Mw0
Max Winter Mw0
Reason Not Completed.