Not reported
BPA queue ID G0682 Terminal status
| Queue ID | G0682 |
|---|---|
| Project name | Not reported |
| Status (as published) | WITHDRAWN |
| Substation | Big Eddy - Spring Creek No 1 line, approximately 28 miles NE of the Big Eddy Substation |
| Point of interconnection | Big Eddy - Spring Creek No 1 230 kV line, approximately 28 miles NE of the Big Eddy Substation |
| County | Klickitat |
| State | WA |
| Voltage | 230 kV |
| Capacity | 300 MW |
| Resource (as published) | Solar/Photovoltaic |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2025-12-31 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Connection Type | GI |
|---|---|
| Interconnection Type | NRIS & ERIS |
| Poi | Big Eddy - Spring Creek No 1 230 kV line, approximately 28 miles NE of the Big Eddy Substation |
| Generator Type | Photovoltaic |
| Fuel Source | Solar |
| Nameplate Mw Total | 459 |
| Max Summer Mw | 300 |
| Max Winter Mw | 300 |
| Reason Not Completed | . |
| Comments | Interconnection Capacity is for 300 MW max at the POI. |