Substation Scout

Not reported

BPA queue ID G0682 Terminal status

Queue IDG0682
Project nameNot reported
Status (as published)WITHDRAWN
SubstationBig Eddy - Spring Creek No 1 line, approximately 28 miles NE of the Big Eddy Substation
Point of interconnectionBig Eddy - Spring Creek No 1 230 kV line, approximately 28 miles NE of the Big Eddy Substation
CountyKlickitat
StateWA
Voltage230 kV
Capacity300 MW
Resource (as published)Solar/Photovoltaic
Resource categorySolar (normalised for filtering)
Target commercial operation2025-12-31
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiBig Eddy - Spring Creek No 1 230 kV line, approximately 28 miles NE of the Big Eddy Substation
Generator TypePhotovoltaic
Fuel SourceSolar
Nameplate Mw Total459
Max Summer Mw300
Max Winter Mw300
Reason Not Completed.
CommentsInterconnection Capacity is for 300 MW max at the POI.

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.