Substation Scout

Not reported

BPA queue ID G0665 Terminal status

Queue IDG0665
Project nameNot reported
Status (as published)WITHDRAWN
SubstationLower Granite or Central Ferry or Central Ferry
Point of interconnectionLower Granite 500kV or Central Ferry 500kV or Central Ferry 230kV
CountyGarfield
StateWA
Voltage500 kV
Capacity750 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2025-12-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiLower Granite 500kV or Central Ferry 500kV or Central Ferry 230kV
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total1125
Max Summer Mw750
Max Winter Mw750
ClusterTransition Late Stage
Reason Not Completed.
CommentsWind 600 MW / Solar 150 MW / 375 MW Battery

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.