Substation Scout

Not reported

BPA queue ID G0662 Terminal status

Queue IDG0662
Project nameNot reported
Status (as published)WITHDRAWN
SubstationPilot Butte to Redmond or Pilot Butte to Ponderosa
Point of interconnectionPilot Butte to Redmond 230kV or Pilot Butte to Ponderosa 230kV
CountyDeschutes
StateOR
Voltage230 kV
Capacity400 MW
Resource (as published)Solar/Photovoltaic
Resource categorySolar (normalised for filtering)
Target commercial operation2025-12-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiPilot Butte to Redmond 230kV or Pilot Butte to Ponderosa 230kV
Generator TypePhotovoltaic
Fuel SourceSolar
Nameplate Mw Total600
Max Summer Mw400
Max Winter Mw400
ClusterTransition Cluster
Reason Not Completed.
Comments400 MW Solar / 200 MW Battery

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.