BPA queue ID G0649 Terminal status
| Queue ID | G0649 |
|---|---|
| Project name | Not reported |
| Status (as published) | WITHDRAWN |
| Substation | Loop into Jones Canyon - Santiam line, .1 mile East of Hwy 26 |
| Point of interconnection | Loop into Jones Canyon - Santiam 230 kV line, .1 mile East of Hwy 26 |
| County | Wasco |
| State | OR |
| Voltage | 230 kV |
| Capacity | 641 MW |
| Resource (as published) | Solar/Photovoltaic |
| Resource category | Solar (normalised for filtering) |
| Target commercial operation | 2023-06-01 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Connection Type | GI |
|---|---|
| Interconnection Type | NRIS & ERIS |
| Poi | Loop into Jones Canyon - Santiam 230 kV line, .1 mile East of Hwy 26 |
| Generator Type | Photovoltaic |
| Fuel Source | Solar |
| Nameplate Mw Total | 641 |
| Max Summer Mw | 641 |
| Max Winter Mw | 641 |
| Reason Not Completed | . |