BPA queue ID G0628 Terminal status

Queue IDG0628
Project nameNot reported
Status (as published)WITHDRAWN
SubstationVantage - Schultz No 1 , or Bettas - Columbia No 1
Point of interconnectionVantage - Schultz No 1 500 kV, or Bettas - Columbia No 1 230 kV
CountyKittitas
StateWA
Voltage500 kV
Capacity125 MW
Resource (as published)Solar/Photovoltaic
Resource categorySolar (normalised for filtering)
Target commercial operation2022-12-31
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiVantage - Schultz No 1 500 kV, or Bettas - Columbia No 1 230 kV
Generator TypePhotovoltaic
Fuel SourceSolar
Nameplate Mw Total125
Max Summer Mw125
Max Winter Mw125
Reason Not Completed.