Substation Scout

Not reported

BPA queue ID G0590 Terminal status

Queue IDG0590
Project nameNot reported
Status (as published)WITHDRAWN
SubstationGrizzly-Summer Lake or Grizzly-Captain Jack line.
Point of interconnectionGrizzly-Summer Lake 500 kV or Grizzly-Captain Jack 500 kV line.
CountyLake
StateOR
Voltage500 kV
Capacity600 MW
Resource (as published)Solar/Photovoltaic
Resource categorySolar (normalised for filtering)
Target commercial operation2021-07-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiGrizzly-Summer Lake 500 kV or Grizzly-Captain Jack 500 kV line.
Generator TypePhotovoltaic
Fuel SourceSolar
Nameplate Mw Total600
Max Summer Mw600
Max Winter Mw600
Reason Not Completed.

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.