Substation Scout

Not reported

BPA queue ID G0567 Terminal status

Queue IDG0567
Project nameNot reported
Status (as published)WITHDRAWN
SubstationNilles Corner Substation
Point of interconnectionNilles Corner Substation
CountyDouglas
StateWA
VoltageNot reported
Capacity5 MW
Resource (as published)Battery/Energy Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2019-06-30
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeERIS
PoiNilles Corner Substation
Generator TypeEnergy Storage
Fuel SourceBattery
Nameplate Mw Total5
Max Summer Mw5
Max Winter Mw5
Reason Not Completed.