Substation Scout

Not reported

BPA queue ID G0554 Terminal status

Queue IDG0554
Project nameNot reported
Status (as published)WITHDRAWN
Substation1) BPA's Big Eddy-Troutdale line, or 2) BPA's Big Eddy-McLoughlin line
Point of interconnection1) BPA's Big Eddy-Troutdale 230 kV line, or 2) BPA's Big Eddy-McLoughlin 230 kV line
CountyHood River
StateOR
Voltage230 kV
Capacity148 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2019-12-31
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS
Poi1) BPA's Big Eddy-Troutdale 230 kV line, or 2) BPA's Big Eddy-McLoughlin 230 kV line
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total148
Max Summer Mw148
Max Winter Mw148
Reason Not Completed.

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.