Substation Scout

Not reported

BPA queue ID G0551 Terminal status

Queue IDG0551
Project nameNot reported
Status (as published)WITHDRAWN
SubstationBPA's Ponderosa Substation.
Point of interconnectionBPA's Ponderosa Substation.
CountyCrook
StateOR
VoltageNot reported
Capacity101 MW
Resource (as published)Solar/Photovoltaic
Resource categorySolar (normalised for filtering)
Target commercial operation2020-12-31
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiBPA's Ponderosa Substation.
Generator TypePhotovoltaic
Fuel SourceSolar
Nameplate Mw Total101
Max Summer Mw101
Max Winter Mw101
Reason Not Completed.
Comments100.5 MW Request