Not reported

BPA queue ID G0550 Terminal status

Queue IDG0550
Project nameNot reported
Status (as published)WITHDRAWN
SubstationMorrow Flat Substation.
Point of interconnectionMorrow Flat 230 kV Substation.
CountyUmatilla
StateOR
Voltage230 kV
Capacity120 MW
Resource (as published)Solar/Photovoltaic
Resource categorySolar (normalised for filtering)
Target commercial operation2020-12-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeERIS
PoiMorrow Flat 230 kV Substation.
Generator TypePhotovoltaic
Fuel SourceSolar
Nameplate Mw Total120
Max Summer Mw120
Max Winter Mw120
Reason Not Completed.