Not reported

BPA queue ID G0528 Terminal status

Queue IDG0528
Project nameNot reported
Status (as published)WITHDRAWN
SubstationPearl substation
Point of interconnectionPearl 230 kV substation
CountyClackamas
StateOR
Voltage230 kV
Capacity150 MW
Resource (as published)Battery/Energy Storage
Resource categoryBattery (normalised for filtering)
Target commercial operation2017-06-30
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeERIS
PoiPearl 230 kV substation
Generator TypeEnergy Storage
Fuel SourceBattery
Nameplate Mw Total150
Max Summer Mw150
Max Winter Mw150
Reason Not Completed.

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.