BPA queue ID G0495 Terminal status

Queue IDG0495
Project nameNot reported
Status (as published)WITHDRAWN
SubstationTroutdale, OR or Camas, WA
Point of interconnectionTroutdale, OR or Camas, WA
CountyClark
StateWA
VoltageNot reported
Capacity60 MW
Resource (as published)Natural Gas/Gas Turbine
Resource categoryGas (normalised for filtering)
Target commercial operation2016-01-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeERIS
PoiTroutdale, OR or Camas, WA
Generator TypeGas Turbine
Fuel SourceNatural Gas
Nameplate Mw Total60
Max Summer Mw60
Max Winter Mw60
Reason Not Completed.
CommentsFES Report issued