Substation Scout

Not reported

BPA queue ID G0463 Terminal status

Queue IDG0463
Project nameNot reported
Status (as published)WITHDRAWN
SubstationBPA's transmission facilities at Ponderosa Substation.
Point of interconnectionBPA's 230 kV transmission facilities at Ponderosa Substation.
CountyLake & Harney
StateOR
Voltage230 kV
Capacity400 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2014-12-31
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiBPA's 230 kV transmission facilities at Ponderosa Substation.
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total400
Max Summer Mw400
Max Winter Mw400
Reason Not Completed.
CommentsWithdrawn on September 6, 2013.

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.