Not reported
BPA queue ID G0459 Terminal status
| Queue ID | G0459 |
|---|---|
| Project name | Not reported |
| Status (as published) | WITHDRAWN |
| Substation | At a point on BPA's Albany-Salem transmsission line within a mile either side of Conser Road. |
| Point of interconnection | At a point on BPA's Albany-Salem 115 kV transmsission line within a mile either side of Conser Road. |
| County | Linn |
| State | OR |
| Voltage | 115 kV |
| Capacity | 65 MW |
| Resource (as published) | Natural Gas/Gas Turbine |
| Resource category | Gas (normalised for filtering) |
| Target commercial operation | 2013-05-01 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Connection Type | GI |
|---|---|
| Interconnection Type | NRIS & ERIS |
| Poi | At a point on BPA's Albany-Salem 115 kV transmsission line within a mile either side of Conser Road. |
| Generator Type | Gas Turbine |
| Fuel Source | Natural Gas |
| Nameplate Mw Total | 65 |
| Max Summer Mw | 65 |
| Max Winter Mw | 45 |
| Reason Not Completed | . |
| Comments | Withdrawn by Customer on December 20,2011. |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.