Substation Scout

Not reported

BPA queue ID G0455 Terminal status

Queue IDG0455
Project nameNot reported
Status (as published)WITHDRAWN
SubstationIn the area of Ione Substation/Kinger Tap.
Point of interconnectionIn the area of Ione Substation/Kinger Tap.
CountyMorrow
StateOR
VoltageNot reported
Capacity50 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2014-12-31
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiIn the area of Ione Substation/Kinger Tap.
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total50
Max Summer Mw50
Max Winter Mw50
Reason Not Completed.

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.