Substation Scout

Not reported

BPA queue ID G0446 Terminal status

Queue IDG0446
Project nameNot reported
Status (as published)WITHDRAWN
SubstationA proposed new substation on BPA's McNary-Coyote Springs transmission line.
Point of interconnectionA proposed new substation on BPA's McNary-Coyote Springs 500 kV transmission line.
CountyMorrow
StateOR
Voltage500 kV
Capacity215 MW
Resource (as published)Natural Gas/Gas Turbine
Resource categoryGas (normalised for filtering)
Target commercial operation2013-05-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS & ERIS
PoiA proposed new substation on BPA's McNary-Coyote Springs 500 kV transmission line.
Generator TypeGas Turbine
Fuel SourceNatural Gas
Nameplate Mw Total240
Max Summer Mw215
Max Winter Mw240
Reason Not Completed.
CommentsWithdrawn by customer; letter instructions received November 15, 2013.

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.