Not reported

BPA queue ID G0434 Terminal status

Queue IDG0434
Project nameNot reported
Status (as published)WITHDRAWN
SubstationAt Emerald PUD Facility bus A-3
Point of interconnectionAt Emerald PUD Facility 12.47 kV bus A-3
CountyLinn
StateOR
Voltage12.5 kV
Capacity11 MW
Resource (as published)Biofuel/Reciprocating Engine
Resource categoryOther (normalised for filtering)
Target commercial operation2012-03-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeERIS
PoiAt Emerald PUD Facility 12.47 kV bus A-3
Generator TypeReciprocating Engine
Fuel SourceBiofuel
Nameplate Mw Total11
Max Summer Mw11
Max Winter Mw11
Reason Not Completed.
CommentsWithdrawn on January 28, 2011.