Substation Scout

Not reported

BPA queue ID G0425 Terminal status

Queue IDG0425
Project nameNot reported
Status (as published)WITHDRAWN
SubstationSummer Lake Subtstation.
Point of interconnectionSummer Lake Subtstation.
CountyLake
StateOR
VoltageNot reported
Capacity103 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2013-12-31
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeERIS
PoiSummer Lake Subtstation.
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total103
Max Summer Mw103
Max Winter Mw103
Reason Not Completed.
CommentsWithdrawn on September 27, 2010.

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.