Substation Scout

Not reported

BPA queue ID G0394 Terminal status

Queue IDG0394
Project nameNot reported
Status (as published)WITHDRAWN
SubstationNot reported
Point of interconnectionNot reported
CountyDeschutes
StateOR
VoltageNot reported
Capacity28 MW
Resource (as published)Biofuel/Reciprocating Engine
Resource categoryOther (normalised for filtering)
Target commercial operation2012-03-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS
Generator TypeReciprocating Engine
Fuel SourceBiofuel
Nameplate Mw Total28
Max Summer Mw28
Max Winter Mw28
Reason Not Completed.
CommentsFAS Study Issued 11/21/2011

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.