Substation Scout

Not reported

BPA queue ID G0393 Terminal status

Queue IDG0393
Project nameNot reported
Status (as published)WITHDRAWN
SubstationRocky Reach - Maple Valley transmission line
Point of interconnection345 kV Rocky Reach - Maple Valley transmission line
CountyKittitas
StateWA
Voltage345 kV
Capacity75 MW
Resource (as published)Solar/Photovoltaic
Resource categorySolar (normalised for filtering)
Target commercial operation2010-12-15
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS
Poi345 kV Rocky Reach - Maple Valley transmission line
Generator TypePhotovoltaic
Fuel SourceSolar
Nameplate Mw Total75
Max Summer Mw75
Max Winter Mw75
Reason Not Completed.
CommentsWithdrawn on 4/8/2014