Substation Scout

Not reported

BPA queue ID G0371 Terminal status

Queue IDG0371
Project nameNot reported
Status (as published)WITHDRAWN
SubstationTBA
Point of interconnectionTBA
CountyGrays Harbor
StateWA
VoltageNot reported
Capacity65 MW
Resource (as published)Biofuel/Reciprocating Engine
Resource categoryOther (normalised for filtering)
Target commercial operation2012-12-31
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeERIS
PoiTBA
Generator TypeReciprocating Engine
Fuel SourceBiofuel
Nameplate Mw Total65
Max Summer Mw65
Max Winter Mw65
Reason Not Completed.
CommentsWithdrawn on May 4, 2010

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.