Substation Scout

Not reported

BPA queue ID G0357 Terminal status

Queue IDG0357
Project nameNot reported
Status (as published)WITHDRAWN
SubstationHEC 115
Point of interconnectionHEC 115
CountyHarney
StateOR
VoltageNot reported
Capacity104 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2010-12-31
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS
PoiHEC 115
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total104
Max Summer Mw104
Max Winter Mw104
Reason Not Completed.
CommentsWithdrawn by Customer on October 4, 2010.

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.