BPA queue ID G0352 Terminal status

Queue IDG0352
Project nameNot reported
Status (as published)WITHDRAWN
SubstationReedsport-Fairview transmission line
Point of interconnectionReedsport-Fairview 115 kV transmission line
CountyCoos
StateOR
Voltage115 kV
Capacity120 MW
Resource (as published)Natural Gas/Gas Turbine
Resource categoryGas (normalised for filtering)
Target commercial operation2013-12-31
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeERIS
PoiReedsport-Fairview 115 kV transmission line
Generator TypeGas Turbine
Fuel SourceNatural Gas
Nameplate Mw Total120
Max Summer Mw120
Max Winter Mw120
Reason Not Completed.
CommentsWithdrawn by Customer on April 12, 2010. 8/12/09: FES review meeting held; FES report available on request. ISIS completed. April 12, 2010: Following review of the ISIS report, customer withdrew the Request by letter.

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.