Not reported
BPA queue ID G0337 Terminal status
| Queue ID | G0337 |
|---|---|
| Project name | Not reported |
| Status (as published) | WITHDRAWN |
| Substation | New substation on BPA's McNary-John Day line |
| Point of interconnection | New substation on BPA's 500 kV McNary-John Day 500 kV line |
| County | Klickitat & Yakima |
| State | WA |
| Voltage | 500 kV |
| Capacity | 200 MW |
| Resource (as published) | Wind Turbine/Wind Turbine |
| Resource category | Wind (normalised for filtering) |
| Target commercial operation | 2011-10-01 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Connection Type | GI |
|---|---|
| Interconnection Type | NRIS |
| Poi | New substation on BPA's 500 kV McNary-John Day 500 kV line |
| Generator Type | Wind Turbine |
| Fuel Source | Wind Turbine |
| Nameplate Mw Total | 200 |
| Max Summer Mw | 200 |
| Max Winter Mw | 200 |
| Reason Not Completed | . |
| Comments | Withdrawn by Customer on June 10, 2009. |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.