Not reported
BPA queue ID G0333 Terminal status
| Queue ID | G0333 |
|---|---|
| Project name | Not reported |
| Status (as published) | WITHDRAWN |
| Substation | Big Eddy-Maupin line |
| Point of interconnection | Big Eddy-Maupin 230 kV line |
| County | Wasco |
| State | OR |
| Voltage | 230 kV |
| Capacity | 200 MW |
| Resource (as published) | Wind Turbine/Wind Turbine |
| Resource category | Wind (normalised for filtering) |
| Target commercial operation | 2010-12-01 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Connection Type | GI |
|---|---|
| Interconnection Type | NRIS |
| Poi | Big Eddy-Maupin 230 kV line |
| Generator Type | Wind Turbine |
| Fuel Source | Wind Turbine |
| Nameplate Mw Total | 200 |
| Max Summer Mw | 200 |
| Max Winter Mw | 200 |
| Reason Not Completed | . |
| Comments | Withdrawn by Customer on March 19, 2009. |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.