BPA queue ID G0331 Terminal status

Queue IDG0331
Project nameNot reported
Status (as published)WITHDRAWN
SubstationHarney-Brasada line near Hampton Substation
Point of interconnectionHarney-Brasada 115 kV line near Hampton Substation
CountyHarney
StateOR
Voltage115 kV
Capacity8 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2009-07-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeERIS
PoiHarney-Brasada 115 kV line near Hampton Substation
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total8
Max Summer Mw8
Max Winter Mw8
Reason Not Completed.
CommentsWithdrawn on August 11, 2016: customer non-responsive. FAS Study Issued March 29, 2008

Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.