Not reported

BPA queue ID G0319 Terminal status

Queue IDG0319
Project nameNot reported
Status (as published)WITHDRAWN
SubstationGoldendale
Point of interconnectionGoldendale 115 kV
CountyKlickitat
StateWA
Voltage115 kV
Capacity20 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2010-07-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeEnergy
PoiGoldendale 115 kV
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total20
Max Summer Mw20
Max Winter Mw20
Reason Not Completed.
CommentsWithdrawn by Customer on March 8, 2012.