BPA queue ID G0310 Terminal status

Queue IDG0310
Project nameNot reported
Status (as published)WITHDRAWN
SubstationNew substation on BPA's McNary-John Day line near Alderdale, Washington
Point of interconnectionNew substation on BPA's 500 kV McNary-John Day line near Alderdale, Washington
CountyKlickitat & Yakima
StateWA
Voltage500 kV
Capacity200 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2011-10-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS
PoiNew substation on BPA's 500 kV McNary-John Day line near Alderdale, Washington
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total200
Max Summer Mw200
Max Winter Mw200
Reason Not Completed.
CommentsWithdrawn on July 30, 2013