Substation Scout

Not reported

BPA queue ID G0298 Terminal status

Queue IDG0298
Project nameNot reported
Status (as published)WITHDRAWN
SubstationLittle Goose Substation
Point of interconnectionLittle Goose 500 kV Substation
CountyColumbia
StateWA
Voltage500 kV
Capacity300 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2009-12-15
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeERIS
PoiLittle Goose 500 kV Substation
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total300
Max Summer Mw300
Max Winter Mw300
Reason Not Completed.
CommentsWithdrawn by Customer on March 11, 2008