Not reported
BPA queue ID G0292 Terminal status
| Queue ID | G0292 |
|---|---|
| Project name | Not reported |
| Status (as published) | WITHDRAWN |
| Substation | Prosser Substation |
| Point of interconnection | Prosser 115 kV Substation |
| County | Benton |
| State | WA |
| Voltage | 115 kV |
| Capacity | 180 MW |
| Resource (as published) | Wind Turbine/Wind Turbine |
| Resource category | Wind (normalised for filtering) |
| Target commercial operation | 2011-07-01 |
| Source dataset | bpa-generation |
Tracked changes
No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →
Additional filed fields
| Connection Type | GI |
|---|---|
| Interconnection Type | ERIS |
| Poi | Prosser 115 kV Substation |
| Generator Type | Wind Turbine |
| Fuel Source | Wind Turbine |
| Nameplate Mw Total | 180 |
| Max Summer Mw | 180 |
| Max Winter Mw | 180 |
| Reason Not Completed | . |
| Comments | Withdrawn on November 23, 2009 |
Fields shown are those promoted into this dataset. The original ISO filing may contain further columns (study reports, agreement dates, milestone flags) that are retained in the pipeline but not all surfaced here. Always confirm against the ISO's published queue before relying on any value.