Not reported

BPA queue ID G0275 Terminal status

Queue IDG0275
Project nameNot reported
Status (as published)WITHDRAWN
Substation20Miles West of Milton-Freewater
Point of interconnection20Miles West of Milton-Freewater
CountyUmatilla
StateOR
VoltageNot reported
Capacity100 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2009-11-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS
Poi20Miles West of Milton-Freewater
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total100
Max Summer Mw100
Max Winter Mw100
Reason Not Completed.
CommentsWithdrawn on January 7, 2013