Not reported

BPA queue ID G0235 Terminal status

Queue IDG0235
Project nameNot reported
Status (as published)WITHDRAWN
SubstationNew Substation near John Day Substation
Point of interconnectionNew Substation near John Day 500kV Substation
CountySherman
StateOR
Voltage500 kV
Capacity200 MW
Resource (as published)Wind Turbine/Wind Turbine
Resource categoryWind (normalised for filtering)
Target commercial operation2009-11-01
Source datasetbpa-generation

Tracked changes

No changes to this filing observed since BPA tracking began on September 22, 2026. Full change log →

Additional filed fields

Connection TypeGI
Interconnection TypeNRIS
PoiNew Substation near John Day 500kV Substation
Generator TypeWind Turbine
Fuel SourceWind Turbine
Nameplate Mw Total200
Max Summer Mw200
Max Winter Mw200
Reason Not Completed.
CommentsWithdrawn by customer email 12/28/2015. FAS Study Issued 7/2/2008