Substation Scout

Freedom substation interconnection queue

1 active project totaling 150 MW in the APS queue, plus 1 with terminal status (shown grayed).

2 APS queue filings name Freedom as the point of interconnection, all in Maricopa County, AZ.

1active projects
150active MW
2total filed
Queue IDProjectkVMWResourceStatus
Q455 Not reported 230 250 Battery Withdrawn
Q357 Not reported 69 150 Battery Active

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with APS before relying on these figures.