Substation Scout

APS request Q596

APS queue ID Q596

Queue request Q596 was listed in the APS interconnection queue at the end of 2025 as a 330 MW project in Yuma County, AZ, according to Berkeley Lab’s queue data file. The filing names North Gila - Hassayampa TL (32.¬∞, - 113.¬∞) as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of August 15, 2029.

Queue IDQ596
Project nameNot reported
Status (as published)Active
SubstationNorth Gila - Hassayampa TL (32.°, - 113.°)
Point of interconnectionNorth Gila - Hassayampa 500kV TL (32.831681°, - 113.787946°)
CountyYuma
StateAZ
Voltage500 kV
Capacity330 MW
Resource (as published)Other
Resource categoryOther (normalized for filtering)
Proposed online date2029-08-15
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Yuma, AZ: 84 requests in the APS queue, 26 active totaling 6,573.1 MW.

Tracked changes

Not tracked. APS rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityArizona Public Service
Interconnection serviceNRIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)Cluster Study
Study phase (as the queue printed it)Phase 1 Cluster Study
Queue date2025-05-13

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first