Queue request Q358 was listed in the APS interconnection queue at the end of 2025 as a 100 MW battery project in Maricopa County, AZ, according to Berkeley Lab’s queue data file. The filing names Colter as its point of interconnection. Its status as of December 31, 2025 was “Active”, with a proposed online date of December 31, 2024.

Queue IDQ358
Project nameNot reported
Status (as published)Active
SubstationColter
Point of interconnectionColter 69kV
CountyMaricopa
StateAZ
Voltage69 kV
Capacity100 MW
Resource (as published)Battery
Resource categoryBattery (normalized for filtering)
Proposed online date2024-12-31
Source datasetBerkeley Lab Queued Up: 2026 Edition (Lawrence Berkeley National Laboratory and GridTracker, CC BY 4.0), requests through December 31, 2025

Same substation and county

Maricopa, AZ: 259 requests in the APS queue, 82 active totaling 24,048 MW.

Tracked changes

Not tracked. APS rows come from an annual snapshot (requests through December 31, 2025), so this site does not compare them week to week.

Additional filed fields

UtilityArizona Public Service
Interconnection serviceNRIS/ERIS
Project typeGeneration
Study phase (standardized by Berkeley Lab)IA Executed
Study phase (as the queue printed it)In Design
Queue date2020-09-30

Capacity is the first resource type’s MW as the data file gives it; a hybrid’s other components are listed under Components and are not added in.

Fields shown are those in Berkeley Lab’s data file, which standardizes each provider’s queue. The provider’s own queue may carry more fields and newer values. Always confirm against it before relying on any value.

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first